Successful and Unsuccessful process of project management:
There was a lot of deadline that we met which is good since that’s what the point of a project plan is. Starting at the beginning of the year with the decision making of who is doing what, then we had to design the wire frames and 5 page where set the deadline on the project a week of advanced of the deadline this way we can have more time to effectively criticise our work between each other. Yet however the people in my team took far too long to complete these tasks making the project plan to suffer a little bit by moving the deadline to the normal time it was meant to be completed by, instead as the project plan suggested a week in advanced, this way we have more time to evaluate the work.  Because I completed my work as the project plan suggested but my team member didn’t this meant and a decision was made to complete other projects will need to be done instead of the one actually needed. At that point exactly that was done while waiting for the work to be completed by my team members I was doing other work for other projects.
When the work was completed we choose both of my sitemap and wireframes designs to be our final designs. My team members work yet it was submitted late it was rushed due to not planning them self what was needed to be done when needed to be done.
The next stage was to make the wireframe designs in iPlotz and the site map in Microsoft Visio at that point everyone in the team including me done the task on time and within the project plan time limit, this was good as now we are starting to stick to the project plan a little bit better as the first time experience wasn’t that great.
After creating our final designs on our advanced software package we had to evaluate it, this was done also in time.
Final comparison between the wireframes was also done on time.
The training was the part that delayed us the most due to strike action taken from the college, this meant that all the dead line needed shifting backwards. There was nothing else to do but move the deadline backwards. As we were getting training and everything was going to plan, another set of delays occurred as coming from the Easter half term break there was no one to teach us due to the teacher having a doctor’s appointment.  This was the lessons where he needed to teach us how to do 2 and 3 column way out in order to create the website as planned. During that lesson the teacher was absent we started creating the top navigation bar as well as the footer.
After the training we go on with actually creating the website, the ideal was to do all the pages as quickly as possible, so we did.  We linked everything together and showed the presentation to our client. At that stage he said that impotents need to be made in order for the projects to be successful and meet all the requirements, we are now at the stage of where everything is adjusted in order to meet these points and complete the project.

Monitoring what was happening with my team was a fairly hard task  as Remy only had a email address which I can only write to, as Abduls monitoring was done a little bit easier as he had a mobile phone which I can call to. When it comes to communication the telephone is the best way as I found out this way I always knew at what stage Abdul is, unlike Remy which took a bit of time to find out exactly what is going on.